Leonardtown Library and Garvey Senior Activity Center

Leonardtown Library and Garvey Senior Activity Center

Project Description: This project will construct the new Leonardtown Library and Garvey Senior Activity Center in Leonardtown, MD. The project site is on the 141 acre Hayden Property off Leonard’s Grant Parkway within the corporate limits of the Town of Leonardtown.

The new library and senior activity center will be an integrated state-of-the-art facility for information resources, education and senior activities. The library will have meeting rooms, technology infrastructure throughout for visitors of all ages, a vending café, a hi-tech specialty classroom, and dedicated areas for adults, teens and children. The senior activity center will benefit from the close proximity of the library, and will also provide exercise, aerobic and fitness rooms, spaces for arts and crafts, as well as quiet rooms. The senior activity center will also provide lounge areas and a commercial kitchen.

The facility will also include outdoor terrace areas, ample parking and linkage to future recreational facilities planned for the County property on which it is being constructed. In addition to the construction of the facility and its associated site improvements, the project will also extend the Town of Leonardtown water main from the adjacent school site to Hollywood Road (MD 245).

St. Mary's County Government - Approved FY2018 Capital Improvement Program
Appropriation Phase Total Project Prior Approval Budget FY2018 Five Year Capital Program Balance to Complete
FY 2019 FY 2020 FY 2021 FY 2022 FY 2023
Architect/Engineering 1,740,000 1,740,000 0 0 0 0 0 0 0
Construction/Site Work 16,147,046 0 16,147,046 0 0 0 0 0 0
Escalation (2.75% per year) 866,552 0 866,552 0 0 0 0 0 0
Construction Management & Testing 629,052 0 629,052 0 0 0 0 0 0
Furniture & Equipment (inc. $100K IT) 990,000 0 990,000 0 0 0 0 0 0
W&S Connection/Imact Fees 135,800 0 135,800 0 0 0 0 0 0
Other (Contingencies) 1,013,217 0 1,013,217 0 0 0 0 0 0
Total Costs 21,521,667 1,740,000 19,781,667 0 0 0 0 0 0

Project Timeline

  • Bid Phase - November 2017 to January 2018
  • Award Phase - January 2018 - May 2018
  • Construction - May 2018- January 2020
  • Furniture & More - January 2020 to March 2020
Library East and West Elevation

For further information, contact Gary Whipple, Capital Projects Manager, 301-475-4200 Ext. *3565